Maine’s first design-build project, Sagadahoc
Bridge was completed one month ahead of schedule. The main span is
420’ – the longest precast segmental span built in the
balanced cantilever fashion in the United States. Gene Figg led a
design charette with the community using consensus voting to gain
input on the various features of the bridge that were beyond the
requirements of the contract. |
|
| Completed: | August 2000 | | Customer: | Maine Department of Transportation | | Design: | Figg Engineering Group | | Contractor: | Flatiron Structures, LLC | | Length: | 2,972' | | Major Award: | Grand Conceptor Award from Colorado ACEC (2000) |
|
|
|